Chapter VII - Of Discharge from Liability on Notes, Bills and Cheques
Section 84
Section 84: Delayed cheque presentment and actual damage
Section 84 gives a drawer or account-holder a limited discharge where delayed cheque presentment causes the actual damage described by the provision.
On this page
Need advice on Section 84?
This article is for general information. Refer to the Negotiable Instruments Act, 1881 official text for the official provisions. If you need professional advice for your situation, contact Bizeneed.
Statutory text
Bare law
(1) Where a cheque is not presented for payment within a reasonable time of its issue, and the drawer or person on whose account it is drawn had the right, at the time when presentment ought to have been made, as between himself and the banker, to have the cheque paid and suffers actual damage through the delay, he is discharged to the extent of such damage, that is to say, to the extent to which such drawer or person is a creditor of the banker to a larger amount than he would have been if such cheque had been paid.
(2) In determining what is a reasonable time, regard shall be had to the nature of the instrument, the usage of trade and of bankers, and the facts of the particular case.
(3) The holder of the cheque as to which such drawer or person is so discharged shall be a creditor, in lieu of such drawer or person, of such banker to the extent of such discharge and entitled to recover the amount from him.
Illustrations: (a) A draws a cheque for Rs. 1,000, and, when the cheque ought to be presented, has funds at the bank to meet it. The bank fails before the cheque is presented. The drawer is discharged, but the holder can prove against the bank for the amount of the cheque.
(b) A draws a cheque at Umballa on a bank in Calcutta. The bank fails before the cheque could be presented in ordinary course. A is not discharged, for he has not suffered actual damage through any delay in presenting the cheque.
Key rule and applicability
The cheque was not presented within a reasonable time, the person had the relevant right to payment when it should have been presented, and actual damage resulted through the delay. Discharge is only to that damage extent. The holder takes the specified creditor position against the banker to the corresponding extent.
Limits and related provisions
Delay alone is insufficient, and bank failure alone does not establish damage caused by that delay. This damages rule does not extend cheque validity or replace the separate conditions for a section 138 prosecution. Any bank recovery is subject to the applicable legal process rather than a guarantee of payment.
Hypothetical business example
Hypothetical: the bank fails before a cheque could have been presented in the ordinary course. The holder checks causation instead of assuming that the drawer is discharged merely because the bank failed; the Act’s second illustration makes that distinction.
Practical decision flow
Establish the reasonable presentment point from the instrument, banking usage and case facts.
Verify the drawer’s then-existing payment entitlement and quantify actual damage caused by delay.
Apply only the corresponding discharge and identify the holder’s resulting claim against the banker.
Practical checklist
Do
- Establish the reasonable presentment point from the instrument, banking usage and case facts.
- Verify the drawer’s then-existing payment entitlement and quantify actual damage caused by delay.
- Apply only the corresponding discharge and identify the holder’s resulting claim against the banker.
Avoid
- Delay alone is insufficient, and bank failure alone does not establish damage caused by that delay. This damages rule does not extend cheque validity or replace the separate conditions for a section 138 prosecution. Any bank recovery is subject to the applicable legal process rather than a guarantee of payment.
Glossary
- Actual damage
- The loss caused through delayed presentment within subsection (1).
- Limited discharge
- Discharge only to the extent of that statutory damage.
Frequently asked questions
Does any late presentment release the whole cheque amount automatically?
No. The right-to-payment and actual-damage conditions must be met, and discharge is limited to the damage extent.
How is reasonable time assessed?
The section refers to the instrument’s nature, trade and banking usage and the particular facts.
What happens to the corresponding claim against the bank?
Subsection (3) places the holder in the specified creditor position to the extent of the discharge.
Need help applying this provision to your situation?
Contact BizeneedLast updated 10 October 2026